8月9日,廣西路建集團(tuan)南寧(ning)沙井至吳(wu)圩公路№TJ1合同段(duan)(簡(jian)稱“沙吳(wu)1標”)那多(duo)高架大橋(qiao)順(shun)利完成橋(qiao)面鋪裝(zhuang)施工(gong)(gong)(gong)。至此,沙吳(wu)1標全線橋(qiao)梁工(gong)(gong)(gong)程全部完工(gong)(gong)(gong),為后(hou)續瀝(li)青路面施工(gong)(gong)(gong)打通斷點、提(ti)供作業面。沙吳(wu)1標正以昂揚奮進姿(zi)態向“十一(yi)”通車目(mu)標發起總攻。
沙吳1標那(nei)多高(gao)架大橋(qiao)橋(qiao)面鋪裝施工順利完成 劉賽妃/攝
為進一步推進工(gong)(gong)程建設,廣(guang)西(xi)路建集團迅速成立沙吳1標保通車指揮(hui)部,召開工(gong)(gong)作部署會,圍繞項目建設難點確立了(le)瀝(li)青(qing)路面(mian)、沙井收(shou)費站及(ji)南壇改線、龍潭服務區“三(san)大攻堅(jian)戰”,重(zhong)新(xin)梳理剩余工(gong)(gong)程量,細化分(fen)解重(zhong)難點工(gong)(gong)程,制(zhi)定詳細有序的施(shi)工(gong)(gong)計劃;同時(shi)從人員、設備、材料(liao)三(san)方面(mian)加大力量投入,加壓奮進,補齊短板(ban),全力推進施(shi)工(gong)(gong)進度。
沙(sha)吳1標保通車推進小(xiao)組(zu)布(bu)置會 曾莉莉/攝
在人(ren)(ren)員方面(mian),廣西路(lu)建(jian)集團抽調已完工(gong)的都巴高速、新柳南(nan)高速及部(bu)分在建(jian)項目(mu)的精兵強將支援沙(sha)吳1標,并根據工(gong)程需要調配與(yu)企業合(he)作密切(qie)、經驗豐富的勞(lao)務班組(zu)進場。當前項目(mu)共有管(guan)理人(ren)(ren)員105人(ren)(ren),勞(lao)務人(ren)(ren)員2129人(ren)(ren),24小時不(bu)間斷施(shi)工(gong),用時3天完成南(nan)壇改線新建(jian)部(bu)分瀝青路(lu)面(mian)施(shi)工(gong),攤(tan)(tan)鋪瀝青3437噸。截至目(mu)前,沙(sha)吳1標攤(tan)(tan)鋪水泥穩(wen)定碎(sui)石混合(he)料(liao)約(yue)76萬噸,攤(tan)(tan)鋪瀝青混合(he)料(liao)約(yue)5.5萬噸。
沙吳1標瀝青上面層試驗(yan)路攤鋪(pu) 劉賽妃/攝
施工(gong)員(yuan)檢測(ce)瀝青溫度 劉賽(sai)妃/攝
此(ci)外,廣西路建集團發揮自身(shen)設備資源優勢,往沙吳1標調(diao)配瀝(li)青攪拌站、瀝(li)青攤鋪機(ji)、挖掘(jue)機(ji)、壓路機(ji)、銑(xian)刨(bao)機(ji)、灑水(shui)車等各類機(ji)械設備投入攻堅戰。當前項(xiang)目共(gong)有163臺(tai)機(ji)械設備開足(zu)馬力運(yun)轉不(bu)停歇。
機(ji)械設備全(quan)力(li)投(tou)入攻堅戰(zhan) 劉(liu)賽妃/攝
沙吳1標(biao)合理(li)制定保供(gong)采備(bei)(bei)方案(an),第(di)一時(shi)(shi)間銜接生產供(gong)應計(ji)劃,落實采購渠道,時(shi)(shi)刻關注項(xiang)目庫存動(dong)態(tai)并(bing)落實專人(ren)負責(ze)梳理(li)所有在途(tu)原(yuan)料信息、發運(yun)情(qing)況。當前,項(xiang)目滿罐滿倉備(bei)(bei)料,累計(ji)備(bei)(bei)料9.8萬噸,其(qi)中墊(dian)層(ceng)和(he)基(ji)層(ceng)備(bei)(bei)料共2萬噸,瀝(li)青結構層(ceng)備(bei)(bei)料7萬噸,水泥砼和(he)機(ji)制砂備(bei)(bei)料0.8萬噸。
機械轟鳴晝夜不息 劉賽妃/攝
項(xiang)目建設全面(mian)提速,7月(yue)(yue)沙吳(wu)1標(biao)水穩層(ceng)施工(gong)(gong)(gong)、瀝(li)青下(xia)層(ceng)面(mian)施工(gong)(gong)(gong)、龍(long)灘服務(wu)區(qu)施工(gong)(gong)(gong)進度明顯加快,當月(yue)(yue)分別完成設計總量(liang)的19%、21%、16%。7月(yue)(yue)23日(ri)(ri),沙吳(wu)1標(biao)完成沙井互通橋面(mian)施工(gong)(gong)(gong);7月(yue)(yue)25日(ri)(ri),瀝(li)青下(xia)層(ceng)面(mian)試驗路順利攤(tan)鋪(pu);8月(yue)(yue)1日(ri)(ri),瀝(li)青中面(mian)層(ceng)試驗路順利攤(tan)鋪(pu);8月(yue)(yue)4日(ri)(ri),沙吳(wu)高(gao)(gao)速首(shou)段(duan)瀝(li)青上面(mian)層(ceng)試驗路順利攤(tan)鋪(pu);8月(yue)(yue)7日(ri)(ri),南壇(tan)改線段(duan)高(gao)(gao)嶺方向右幅已(yi)接通原高(gao)(gao)速路;8月(yue)(yue)9日(ri)(ri),項(xiang)目全線橋梁工(gong)(gong)(gong)程(cheng)順利完工(gong)(gong)(gong)……截至目前,沙吳(wu)1標(biao)路基(ji)工(gong)(gong)(gong)程(cheng)、路面(mian)墊層(ceng)、水穩底基(ji)層(ceng)已(yi)全部完工(gong)(gong)(gong),防(fang)護工(gong)(gong)(gong)程(cheng)、橋涵(han)工(gong)(gong)(gong)程(cheng)、沙井收費站完成率達95%。
沙井(jing)互通 劉賽妃/攝(she)
沙吳1標(biao)瀝青中面層試驗路攤鋪 劉賽妃(fei)/攝