11月22日,南(nan)寧(ning)市水環境綜合治(zhi)理工(gong)作指揮部督(du)(du)查督(du)(du)辦組對集團公司以高度(du)的政(zheng)治(zhi)責任感(gan)和緊(jin)迫感(gan),多舉(ju)措(cuo)開展(zhan)心(xin)圩江黑(hei)臭水體治(zhi)理工(gong)作并(bing)取得了良(liang)好(hao)成效,進行通報(bao)表揚(yang)。
通報文件截圖
心圩江(jiang)項(xiang)目自開工(gong)以來(lai),充分發揮管理(li)優(you)勢、技術優(you)勢,穩步推(tui)進(jin)心圩江(jiang)河道綜合整(zheng)治各項(xiang)工(gong)作,助力南(nan)寧市河道治理(li)和景觀提升(sheng),并取得(de)了(le)良好的(de)成效(xiao),交出(chu)了(le)優(you)秀的(de)“路建(jian)答卷”,項(xiang)目施工(gong)的(de)好經驗、好做(zuo)法得(de)到各級單位的(de)肯定(ding)。
五龍橋段整治(zhi)工(gong)程(cheng)(cheng)是心圩江環(huan)境(jing)綜(zong)合治(zhi)理工(gong)程(cheng)(cheng)的重點(dian)工(gong)程(cheng)(cheng)、控制性(xing)工(gong)程(cheng)(cheng),包含約850米的樁板式(shi)擋墻工(gong)程(cheng)(cheng)、五龍橋工(gong)程(cheng)(cheng)、污水(shui)管網完善(shan)工(gong)程(cheng)(cheng)。該工(gong)程(cheng)(cheng)地處城中(zhong)村,兩岸是沿線(xian)住房,沒有施(shi)工(gong)便道(dao),河(he)里都是淤泥,給(gei)施(shi)工(gong)帶來極大難題。
為(wei)順利完成五(wu)龍橋(qiao)段整治(zhi)工(gong)(gong)程(cheng),心圩江項(xiang)目迎(ying)難(nan)(nan)而上(shang),給出(chu)“路(lu)建方案”破解施(shi)(shi)工(gong)(gong)難(nan)(nan)題。項(xiang)目一是在(zai)河中間搭建450米長(chang)的(de)鋼棧橋(qiao),作為(wei)施(shi)(shi)工(gong)(gong)便道及施(shi)(shi)工(gong)(gong)平(ping)臺,克(ke)服(fu)機(ji)械進(jin)出(chu)、材料運輸困難(nan)(nan);二是采用全鋼護筒跟進(jin)施(shi)(shi)工(gong)(gong),克(ke)服(fu)五(wu)龍橋(qiao)段整治(zhi)程(cheng)樁基(ji)施(shi)(shi)工(gong)(gong)鉆進(jin)過程(cheng)中因地質條件差(cha)存在(zai)塌孔情況的(de)難(nan)(nan)題;三是緊緊把握住旱季施(shi)(shi)工(gong)(gong)黃金期(qi)(qi),盤點剩余工(gong)(gong)程(cheng)量,科(ke)學優化施(shi)(shi)工(gong)(gong)組織,倒排工(gong)(gong)期(qi)(qi),領導班(ban)子24小(xiao)時在(zai)施(shi)(shi)工(gong)(gong)現場蹲點值(zhi)班(ban),上(shang)足施(shi)(shi)工(gong)(gong)人員(yuan)和機(ji)械設備,采取“白+黑”工(gong)(gong)作模式,24小(xiao)時輪班(ban)轉(zhuan)換,鋪開施(shi)(shi)工(gong)(gong)作業面,全力加快項(xiang)目建設進(jin)度(du)。
面對“迅速完成涉水(shui)施(shi)(shi)工作業內(nei)容”的“急、難(nan)、重(zhong)”要(yao)求,項目根據現(xian)場施(shi)(shi)工力量需求,在集團公司、一公司的支持下,臨時引進3支施(shi)(shi)工經(jing)驗豐富的勞務隊伍,共計150余人,突(tu)擊攻(gong)堅五(wu)龍橋(qiao)段樁板式擋墻工程(cheng)和五(wu)龍橋(qiao)工程(cheng)樁基、承臺、擋土板、墩(dun)柱、現(xian)澆(jiao)梁等工程(cheng)內(nei)容。
在現場施(shi)(shi)工(gong)(gong)(gong)(gong)力(li)(li)量的不斷優(you)化調(diao)配(pei)與現場施(shi)(shi)工(gong)(gong)(gong)(gong)管理的持續強(qiang)化下,項目開啟“3倍(bei)速”攻堅(jian)模式,不斷優(you)化調(diao)配(pei)現場施(shi)(shi)工(gong)(gong)(gong)(gong)力(li)(li)量,強(qiang)化現場施(shi)(shi)工(gong)(gong)(gong)(gong)管理力(li)(li)度,原本(ben)至少需要15天施(shi)(shi)工(gong)(gong)(gong)(gong)工(gong)(gong)(gong)(gong)期的工(gong)(gong)(gong)(gong)程內容,僅用(yong)5天時間便完(wan)成施(shi)(shi)工(gong)(gong)(gong)(gong)。心圩江項目以實際行動再(zai)創“路建(jian)速度”,凸顯集團(tuan)公司突(tu)擊攻堅(jian)能力(li)(li),交出(chu)優(you)秀(xiu)的“路建(jian)答卷”。
目前,心圩江項目整體施工任務(wu)已完成超過(guo)95%,接下來(lai),項目將進一步優化施工組織,注重生態(tai)環保,加快(kuai)施工進度,全力攻堅管網(wang)完善(shan)工程、游憩建筑和(he)服(fu)務(wu)建筑等(deng)工程剩余施工內容。
五龍橋段整(zheng)治工程(cheng)效果(guo)圖
五龍橋段整治工程施工現場
五龍(long)橋段整治工程建設(she)現狀
心圩江項目(mu)青年(nian)攻(gong)堅(jian)隊風采