10月11日,集團公(gong)司(si)融(rong)河(he)四分部(bu)主線(xian)瀝(li)(li)青上(shang)面(mian)(mian)層攤鋪(pu)完(wan)成(cheng)(cheng),標志著融(rong)河(he)四分部(bu)20.3Km主線(xian)瀝(li)(li)青路面(mian)(mian)工程全部(bu)完(wan)成(cheng)(cheng),項(xiang)目(mu)主體工程任務(wu)基本完(wan)成(cheng)(cheng),成(cheng)(cheng)為融(rong)河(he)高速公(gong)路首個完(wan)成(cheng)(cheng)主線(xian)瀝(li)(li)青施(shi)工的(de)標桿項(xiang)目(mu),離11月28日通車目(mu)標再邁出關(guan)鍵一(yi)步。
瀝青(qing)路面線(xian)形順直(zhi)
融河四分部率先完成主線瀝青上面層攤鋪施工
奮斗一線,保證施工建設有序
融水(shui)至(zhi)河(he)池(chi)(chi)高速公(gong)(gong)路(lu)是(shi)廣西(xi)(xi)交通(tong)網(wang)“橫2線(xian)”賀(he)州(zhou)(靈峰)至(zhi)隆林(lin)(板壩)公(gong)(gong)路(lu)支(zhi)線(xian)——桂林(lin)至(zhi)河(he)池(chi)(chi)高速公(gong)(gong)路(lu)的(de)重要組成路(lu)段,全線(xian)挺進柳州(zhou)、河(he)池(chi)(chi)多個貧(pin)(pin)困(kun)山(shan)區,是(shi)廣西(xi)(xi)深度貧(pin)(pin)困(kun)縣羅城仫(mu)佬(lao)族自治(zhi)縣有史以來(lai)的(de)第一條高速公(gong)(gong)路(lu)。融河(he)高速公(gong)(gong)路(lu)建成通(tong)車后,貧(pin)(pin)困(kun)戶(hu)所種植的(de)核桃(tao)、糖料蔗、花卉(hui)苗(miao)圃(pu)及蠶絲等(deng)特(te)色高經濟效益農(nong)作(zuo)物可通(tong)過“高速直通(tong)道”快速銷(xiao)售至(zhi)柳州(zhou)、桂林(lin)、南寧等(deng)相對發(fa)達地(di)區,使沿線(xian)貧(pin)(pin)困(kun)地(di)區享受到高速路(lu)通(tong)車后實(shi)實(shi)在(zai)在(zai)的(de)經濟福(fu)利(li)。
融河高速公路(lu)沿線民房(fang)分散,許(xu)多群眾身(shen)居大山深處,山路(lu)崎嶇,往往需要數小時才能到達(da)臨近的村(cun)屯,極少有機會能走出大山。
集團公司融河(he)四分(fen)部(bu)全(quan)體參建(jian)者(zhe)舍棄(qi)過很多次休假的機會,埋頭苦干(gan)、克難攻堅。2020年新冠肺炎疫情,延誤了項目(mu)員(yuan)(yuan)工(gong)返崗復(fu)工(gong)時(shi)間(jian),但熄滅不了項目(mu)員(yuan)(yuan)工(gong)復(fu)崗復(fu)業(ye)的工(gong)作激情。自復(fu)工(gong)復(fu)產以來,半(ban)幅架通(tong)、全(quan)幅架通(tong),遷民房、拆高壓鐵塔,水穩施工(gong)、瀝(li)青攤鋪,項目(mu)各節(jie)點工(gong)程(cheng)有條不紊的展開(kai)推(tui)進(jin),工(gong)程(cheng)進(jin)度步步領(ling)先。國(guo)慶(qing)中(zhong)秋“雙節(jie)”期(qi)(qi)間(jian),項目(mu)49名管理人(ren)員(yuan)(yuan)、24人(ren)瀝(li)青班(ban)組、213人(ren)施工(gong)勞務(wu)作業(ye)隊伍全(quan)部(bu)在崗,堅持奮(fen)斗在施工(gong)一線(xian),為項目(mu)“通(tong)車前(qian)最后一公里”保駕護(hu)航。國(guo)慶(qing)中(zhong)秋“雙節(jie)”期(qi)(qi)間(jian),融河(he)四分(fen)部(bu)全(quan)體參建(jian)者(zhe)主(zhu)動放棄(qi)節(jie)假日休息時(shi)間(jian),奮(fen)斗在項目(mu)建(jian)設一線(xian)。
嚴格管理,保證施工安全質量
融河四(si)分部全線20.3Km路面(mian)瀝(li)青(qing)結構層為2.5cm厚RAC-10F橡膠瀝(li)青(qing)混(hun)凝(ning)土(tu)功能層+8cm厚AC-25C瀝(li)青(qing)混(hun)凝(ning)土(tu)下面(mian)層+6cm厚AC-20C改性瀝(li)青(qing)混(hun)凝(ning)土(tu)中(zhong)面(mian)層+4cm厚橡膠瀝(li)青(qing)混(hun)凝(ning)土(tu)上面(mian)層,各個施(shi)工步驟嚴格按照技術方案標準施(shi)工。
2019年12月30日,融河四分部在K85+700—K86+300右幅進行(xing)瀝青(qing)(qing)(qing)下面層試(shi)驗路攤鋪,正(zheng)式拉開瀝青(qing)(qing)(qing)攤鋪施(shi)(shi)工(gong)(gong)序幕。施(shi)(shi)工(gong)(gong)以來,項目堅(jian)持(chi)做到(dao)開展一(yi)次(ci)施(shi)(shi)工(gong)(gong)作業(ye)、進行(xing)一(yi)次(ci)安全(quan)技術交底,嚴格把控瀝青(qing)(qing)(qing)原材(cai)料生(sheng)產、運輸(shu),瀝青(qing)(qing)(qing)混凝土攤鋪、碾(nian)壓(ya)等各個環節,各崗(gang)位(wei)人員各司其職、恪盡(jin)職責,全(quan)力確保(bao)瀝青(qing)(qing)(qing)施(shi)(shi)工(gong)(gong)質(zhi)量。在施(shi)(shi)工(gong)(gong)安排上,瀝青(qing)(qing)(qing)班組以隊為單(dan)位(wei),輪流上崗(gang),做到(dao)“雨天修整機(ji)械、晴(qing)天趕工(gong)(gong)追速”,在保(bao)證瀝青(qing)(qing)(qing)施(shi)(shi)工(gong)(gong)“五加(jia)二、白加(jia)黑”24小時施(shi)(shi)工(gong)(gong)的同(tong)時,保(bao)證施(shi)(shi)工(gong)(gong)作業(ye)人員的休息時間,保(bao)障施(shi)(shi)工(gong)(gong)作業(ye)人員安全(quan)。
此外(wai),項目(mu)全程跟進部署(shu),克(ke)服(fu)雨季時(shi)間長降水多、原材料(liao)供應緊張、機械設備及人員(yuan)不足(zu)、工作面(mian)不連(lian)貫(guan)等諸多困難,施(shi)工用時(shi)僅10個月,全部完(wan)成(cheng)路面(mian)瀝(li)青(qing)(qing)工程量(liang),全力沖(chong)刺融(rong)河(he)(he)高速(su)公(gong)路建成(cheng)通車目(mu)標。融(rong)河(he)(he)四分(fen)部瀝(li)青(qing)(qing)班組連(lian)續作戰72小(xiao)時(shi),全力攻堅(jian)項目(mu)瀝(li)青(qing)(qing)上面(mian)層攤鋪工程量(liang)。
施(shi)工(gong)(gong)(gong)至今,項目已進(jin)入最(zui)(zui)后的(de)建(jian)成通車(che)沖刺階段。為(wei)此,項目實時跟進(jin)剩余(yu)工(gong)(gong)(gong)程量,合(he)理(li)部(bu)署(shu)剩余(yu)施(shi)工(gong)(gong)(gong)節點目標。下一(yi)步,項目將(jiang)重(zhong)點攻(gong)堅(jian)融河五(wu)分部(bu)瀝(li)青施(shi)工(gong)(gong)(gong)工(gong)(gong)(gong)作,繼續保持時不我待的(de)工(gong)(gong)(gong)作責任感(gan),積極發揚“特別能(neng)(neng)(neng)吃苦(ku)、特別能(neng)(neng)(neng)戰斗、特別能(neng)(neng)(neng)奉獻”路(lu)建(jian)鐵軍精(jing)神,全(quan)力(li)攻(gong)堅(jian)剩余(yu)工(gong)(gong)(gong)程量,以完工(gong)(gong)(gong)通車(che)驗收為(wei)工(gong)(gong)(gong)作第一(yi)要(yao)務,吹好最(zui)(zui)后一(yi)口哨(shao)、站好最(zui)(zui)后一(yi)班崗,全(quan)力(li)保障11月28日融河高(gao)速公(gong)路(lu)順利(li)建(jian)成通車(che)。力爭(zheng)融河路(lu)上(shang)再創(chuang)路(lu)建輝(hui)煌,鋪就(jiu)沿線群眾幸福小(xiao)康道路(lu)。