越(yue)南機場4標掃清阻工障(zhang)礙(ai) 策馬奔(ben)騰戰旱季
經過越南交通部、河內(nei)市(shi)征(zheng)地拆遷(qian)辦、地方政府(fu),業主和施(shi)工單位的不斷努力(li),越南機(ji)場4標長期阻工的問(wen)題得到有效解決。目(mu)前(qian)項目(mu)正組織(zhi)大量機(ji)械設備和材料投入(ru)旱季攻(gong)堅戰,外業施(shi)工策馬奔騰、成績喜人(ren)。
自10月(yue)4日直至11月(yue)10日,項目(mu)(mu)施(shi)工(gong)(gong)受到(dao)阻(zu)擾,外業(ye)施(shi)工(gong)(gong)一度(du)(du)處于停(ting)滯狀(zhuang)態。為此,項目(mu)(mu)多(duo)次主動與當地政府部門和(he)業(ye)主、村民進行協調,以求(qiu)盡早(zao)恢復施(shi)工(gong)(gong)。在越南(nan)交通部和(he)河內市政府的(de)(de)(de)大(da)力(li)支持下,在11月(yue)10日以后,項目(mu)(mu)得以逐步恢復施(shi)工(gong)(gong),為搶回落后的(de)(de)(de)進度(du)(du),項目(mu)(mu)按(an)照越南(nan)交通部和(he)業(ye)主要(yao)求(qiu)增強(qiang)施(shi)工(gong)(gong)力(li)量(liang),并(bing)加大(da)對施(shi)工(gong)(gong)隊的(de)(de)(de)支持和(he)指導,要(yao)求(qiu)施(shi)工(gong)(gong)隊把施(shi)工(gong)(gong)計(ji)(ji)劃細(xi)化到(dao)天(tian)(tian),按(an)天(tian)(tian)完成計(ji)(ji)劃,進度(du)(du)現象得到(dao)極大(da)改變。
截止到12月(yue)6日,原來受阻工(gong)(gong)(gong)Km6+000至(zhi)Km6+800段路(lu)(lu)基及路(lu)(lu)面基層(ceng)工(gong)(gong)(gong)程量已(yi)全(quan)部完成(cheng),剩余瀝青路(lu)(lu)面有(you)望在12月(yue)20日前完成(cheng),項目同(tong)步展開照(zhao)明、綠化、交安工(gong)(gong)(gong)程和線外輔道工(gong)(gong)(gong)程。截止至(zhi)12月(yue)6日,項目完成(cheng)產(chan)值(zhi)約為(wei)13500萬(wan)元,完成(cheng)原有(you)效合(he)同(tong)價(jia)的98%。

項目開展(zhan)照明(ming)和綠化分項工(gong)(gong)程施工(gong)(gong)

主線(xian)左幅Km6+671—750段基層施工

主線右(you)幅Km5+422.5—681段瀝青上面層(ceng)施工

主線左幅輔道Km0+081—308.39段水(shui)泥混(hun)凝土路面施(shi)工(gong)