東(dong)天(tian)2標路面(mian)施工突飛猛(meng)進
11月(yue)上旬,受(shou)連續雨水天氣(qi)的影響,東天2標路(lu)面施(shi)(shi)(shi)工(gong)進度(du)受(shou)阻,未能(neng)達到預(yu)期的施(shi)(shi)(shi)工(gong)進度(du),在項(xiang)目經理許力的帶領下,項(xiang)目通過增加勞務工(gong)人,輪班開展連續施(shi)(shi)(shi)工(gong)作業、開展夜間施(shi)(shi)(shi)工(gong)作業等一(yi)系列行(xing)之有(you)效的措施(shi)(shi)(shi),有(you)力地保證了水泥混凝土路(lu)面施(shi)(shi)(shi)工(gong)的進度(du)。
截(jie)止11月(yue)23日,項目已累(lei)計(ji)完成水泥混(hun)凝土路面15km,并以每天(tian)550m至600m的進(jin)度穩步推(tui)進(jin),而且施(shi)工進(jin)度和(he)工程質(zhi)量、現場安(an)全管(guan)理都(dou)得到業主單位(wei)和(he)監理單位(wei)的交口(kou)稱贊。
下一步,項目(mu)將加快K72+000~K83+198.18段新線路基成(cheng)型(xing),抓(zhua)緊鋪筑碎石(shi)墊層(ceng)(ceng)和級配碎石(shi)底基層(ceng)(ceng);加強路面施(shi)(shi)(shi)工組織安排(pai),盡(jin)快完成(cheng)K60+000~K72+000水(shui)泥(ni)混凝土(tu)路面施(shi)(shi)(shi)工;同(tong)時加快K44+740~K60+000水(shui)穩(wen)層(ceng)(ceng)施(shi)(shi)(shi)工進度,使水(shui)穩(wen)層(ceng)(ceng)、封層(ceng)(ceng)和砼面層(ceng)(ceng)施(shi)(shi)(shi)工銜接緊湊,達到連續(xu)、均衡施(shi)(shi)(shi)工。