4月12日,龍(long)水2標最(zui)后一(yi)根(gen)橋(qiao)梁樁基砼澆筑順利完成,領跑崇水路橋(qiao)梁樁基施工速度第(di)一(yi),為項目橋(qiao)梁上部(bu)結構施工和架(jia)梁工作的順利開(kai)展奠定了(le)良好的基礎(chu)。
龍水2標(biao)全線共有6座(zuo)跨(kua)線橋,樁(zhuang)基(ji)42根,全部采(cai)用(yong)(yong)沖(chong)孔灌注樁(zhuang)。龍水2標(biao)橋梁施(shi)工(gong)(gong)從2017年8月開(kai)工(gong)(gong)來,投入充足的設備和人力資源進行(xing)橋梁樁(zhuang)基(ji)鉆(zhan)孔、澆筑施(shi)工(gong)(gong),并加(jia)強過程質量控制,嚴(yan)格按照專項施(shi)工(gong)(gong)方案(an)進行(xing)交底、培訓,充分利用(yong)(yong)地形優勢條件,緊抓施(shi)工(gong)(gong)重點(dian)位置和關鍵環節,不斷(duan)推進了樁(zhuang)基(ji)施(shi)工(gong)(gong)的進度,加(jia)快墩柱(zhu)、蓋梁等(deng)的施(shi)工(gong)(gong),為2018年旱季施(shi)工(gong)(gong)“大干100天”搶抓工(gong)(gong)作面。